SOP: DTI SH85/86 Jointfiler Application

Standard Operating Procedure for using DTI SH85/86 Jointfiler to fill and repair cracks in concrete floors, including preparation, filling, leveling, and cure time requirements.

Product

DTI SH85/86 Jointfiler

Document Type

Standard Operating Procedure

Dwell Time

15 Minutes

Cure Time

3 Hours (no foot traffic)

Application Procedure

  1. Clean the crack. Use a stiff brush to remove any debris from the crack before applying any product.
  2. Insert the joint filler. Use the Dual Cartridge Gun with SH85 Joint Fill to insert the filler into the crack.
  3. Level the filler. Level the filler so it sits flush with the surrounding concrete surface.
  4. Trim excess material. After 15 minutes, allow the material to sit, then use a trowel or shaving tool to remove any excess.
  5. Secure the area. Block off the treated area from all foot traffic for at least 3 hours to allow the product to fully cure.

Equipment and Materials

  • Stiff brush (for crack preparation)
  • Dual Cartridge Gun
  • DTI SH85 Joint Fill cartridge
  • Trowel or shaving tool
  • Perimeter barriers / caution tape