How Do You Specify a Warehouse Slab and Its Resinous Floor System?
Make 8 slab decisions before the pour, then specify the resinous flooring in 3 parts: General, Products and Execution under the 09 67 23 framework. Keep structural design separate from coating qualification and state measurable, product-specific acceptance criteria. The original slab checklist remains below; the added outline explains what the flooring section needs.
By Ryan Stevenson · August 6, 2026 · 14
A warehouse floor spec is a set of decisions. The good ones make those decisions explicitly, in writing, with numbers that can be measured and enforced. The bad ones make the same decisions by default - and the defaults are what fail.
At DTI we review floor specifications every week, across 2,000+ projects and 25+ industries, and the failures follow a pattern: it is almost never the decision the spec made badly. It is the decision the spec never made at all. This checklist is how to find those silences before concrete does. It is structured around the questions owners, GCs, and spec reviewers actually ask us.
What should a warehouse floor spec actually contain?
Eight decisions. If any one of them is missing, someone else - the developer's standard detail, the low bidder, or physics - will make it for you.
1. The loads, defined completely. Uniform storage loads, rack post loads with baseplate size and spacing, wheel loads from the heaviest lift truck, and any line loads. A spec that only states pounds per square foot has described one of four load types.
2. Slab thickness and flexural strength derived from those loads. Slabs-on-ground fail in flexure, not compression, so the spec needs a modulus of rupture target verified by beam test and a thickness produced by analysis (ACI 360R) - not a compressive strength number and a thickness copied from the last project.
3. The subgrade, specified and verified. A target k-value with the compaction and subbase requirements to deliver it, checked in the field before the pour. The best slab design in the world sits on whatever is under it.
4. Flatness, specified for the traffic type. Ff/Fl numbers (ASTM E1155) for free-movement areas, and a separate defined-traffic tolerance for VNA aisles and fixed paths. One blanket flatness number for both is the single most common spec error we see.
5. Joints, designed with load transfer detailed. Joint type, spacing, dowels, and a layout coordinated with the racking plan so posts do not land on free edges. Slabs hold; joints are where floors decide whether they last.
6. The surface system, matched to exposure. Densified and polished, coated, or topped - chosen from the actual abrasion, chemical, and thermal exposure, and only after moisture testing.
7. Special conditions, addressed by name. Cold storage, automation (AGV/AMR), manufacturing zones, and chemical areas each carry their own requirements. If the facility has one of these and the spec does not mention it, the spec is incomplete.
8. Lifecycle and construction sequence, planned. The system selected on cost of ownership rather than first cost, with cure, testing, and sequencing requirements written in.
How do I use this to review a spec that crosses my desk?
Mark every line one of three ways: pass, fail, or silent. Passes are fine. Fails are negotiable. The silences are the danger - a spec that says nothing about subgrade verification or joint load transfer has not avoided those decisions; it has delegated them to the least accountable party on the project.
Is one checklist enough for a real project?
No - and that is the honest answer. Each of the eight decisions above opens into its own set of checkpoints: flatness alone has eight, joints have eight, cold storage has eight. That is why we bound the complete set into one document: The Warehouse Floor Spec Handbook - twelve checklists, ninety-six checkpoints, standards-referenced, covering flatness, joints, load capacity, VNA and racking, distribution centers, cold storage, coatings, manufacturing, automation readiness, lease negotiation, and lifecycle cost.
Download the free handbook here. It is built to sit next to a spec while you review it.
For the technical deep dives behind each checklist, The Floor Front - our LinkedIn newsletter - published the full twelve-part warehousing series this year.
What if the spec is already written, or the floor is already poured?
Then the checklist becomes an assessment tool instead of a design tool. DTI evaluates existing floors against the same framework - floor repair and overlay, coatings, polished concrete, and sealing systems - across commercial and industrial facilities nationwide.
Specifying or evaluating a floor in the next 12 months? Request a free pre-spec consultation or call (209) 879-9674. We will work the checklist against your spec with you, line by line.
How do you write the resinous flooring spec (CSI 09 67 23)?
Use the 09 67 23 resinous-flooring framework to organize responsibilities, materials and execution. The federal example reviewed here is the narrower UFGS 09 67 23.13 section for troweled resinous flooring, not a universal specification for every resin chemistry. Its selectable values must be edited for the project and coordinated with the selected manufacturer's current instructions.
Part 1, General
Require system product data, safety data, relevant test reports, drawings of joints and terminations, color and texture samples, installer qualifications and maintenance instructions. Name who reviews each submittal and approves the mock-up before production. Establish a pre-installation meeting and coordinate access, protection, sequencing and warranty obligations.
The federal guide calls for a full-thickness mock-up on a 96 inch square area and mounted samples at least 12 inches square. Its qualification clause offers five similar installations in successful service for five years, and its warranty clause offers a two-year term. Qualification and warranty numbers are editable guide-spec choices, not universal minimums or a DTI warranty.
Federal guide specification: troweled resinous flooring
Part 2, Products
Name the complete system and nominal thickness by zone, not simply epoxy. Identify primer, body coat or mortar, aggregate, grout and topcoat, including any moisture treatment. State chemical exposures, concentrations, temperatures and contact duration; require evidence for the selected system rather than borrowing a rating from another product.
Specify required properties with their test methods and conditions so results can be compared meaningfully. Detail cove height and radius, drains, cracks, moving joints, transitions, color, gloss, texture and applicable VOC requirements. The federal troweled example uses a nominal 3/16 inch topping with a tolerance of plus or minus 1/16 inch; this does not establish thickness for broadcast epoxy or urethane cement.
Federal guide specification: troweled resinous flooring
Part 3, Execution
Define substrate inspection, moisture testing, repairs, mechanical preparation, profile verification, adhesion evaluation and environmental monitoring before application. Assign responsibility for unacceptable conditions and require approval of the corrective work. Separate foot traffic, rolling loads, wet cleaning and full chemical service when stating cure and release criteria.
Write field acceptance, repair of rejected areas, final cleaning and protection into the specification. The federal troweled example requires concrete at least 28 calendar days old and a dry prepared substrate at least 60°F when application begins. These are that guide's provisions, not a general promise that any floor is ready at that age or temperature.
Federal guide specification: troweled resinous flooring
What moisture limits and concrete age should the spec use?
ASTM F2170 measures internal relative humidity; ASTM F1869 measures moisture vapor emission using anhydrous calcium chloride. They report different properties and their results are not interchangeable. Write the current applicable procedure, test locations, conditioning, reporting and the installed system's acceptance limit into the project documents.
The federal guide offers 75% RH and alternative emission limits of 3 or 4.5 lb per 1,000 sq ft per 24 hours as selectable values. It explicitly directs the specifier to select the test and acceptable moisture levels from the manufacturer's written instructions. Those examples are not limits established by the ASTM test methods or default acceptance for all epoxy.
If results exceed the selected system's limit, investigate the moisture source and obtain an approved, compatible treatment or revised system. Do not assume a generic mitigation primer solves every moisture condition. Document the resulting acceptance criteria before application.
Age also depends on the system. Against the federal guide's 28-day concrete requirement, one polyurethane cement data sheet permits green concrete typically 7 to 10 days old under its stated substrate and moisture conditions. That exception belongs to that product and does not waive testing or permit early application of unrelated coatings.
Federal guide specification: troweled resinous flooring
Manufacturer data: polyurethane cement and young concrete
ASTM F2170: in-situ relative humidity measurement
ASTM F1869: calcium-chloride moisture vapor emission test
What profile and adhesion requirements should the spec state?
Require removal of contaminants and weak material before creating the specified mechanical profile. A reviewed manufacturer preparation guide gives CSP 3 to 5 as its typical recommendation and directs the installer to the current product data sheet. This is not an ICRI rule assigning one CSP range to every coating thickness.
Write the required profile for the actual primer and complete floor build, the verification method and acceptance of edges and repairs. Do not assume grinding or shot blasting alone proves the profile was achieved. The reviewed guide does not recommend acid etching.
The same guide calls for substrate pull-off strength of at least 218 psi (1.5 MPa). That is the manufacturer's substrate requirement, not a universal ASTM D7234 acceptance value. ASTM D7234 evaluates coating pull-off adhesion and identifies the weakest failure plane; state the test arrangement, cure, reporting, failure mode and agreed acceptance criteria separately.
Manufacturer guide: substrate assessment and surface preparation
ASTM D7234: pull-off adhesion of coatings on concrete
How do conditions, cure and acceptance stay measurable?
Use the selected system's limits for air and substrate temperature, relative humidity and dew point, and record conditions during the required period. Do not merge a guide specification's starting temperature with another product's curing schedule. Require adequate lighting and protection from dust, water and other trades.
Separate structural floor tolerances, coating thickness and finished-topping smoothness. The federal troweled example limits variation to 1/8 inch under an 8 foot straightedge; that is not an F-number specification. ASTM E1155 measures FF and FL for random-traffic floor evaluation and is not intended to evaluate fixed-path vehicle systems.
Agree on thickness verification and any destructive-test repair before installation. If traction testing is required, state a method and acceptance criteria appropriate to the installed coating and intended contaminants, with manufacturer guidance. No universal friction value or appearance alone establishes slip safety.
The retained FAQ summaries below are planning guidance, not project acceptance criteria: do not select slab strength by a generic PSI band or use a universal CSP range. F-min and defined-traffic acceptance must be specified separately from ASTM E1155 FF/FL testing. The structural designer and system manufacturer must resolve the actual requirements.
Federal guide specification: troweled resinous flooring
ASTM E1155/E1155M: floor flatness and levelness numbers
One-page 09 67 23 outline
| Part | Article | What to write | Verified example or decision |
|---|---|---|---|
| 1 General | Submittals | Product and safety data, reports, drawings, samples and care instructions. | Federal guide: mounted samples at least 12 inches square. |
| 1 General | Qualifications | Relevant installations, installer competence and review responsibility. | Federal selectable example: five similar installations in service for five years. |
| 1 General | Mock-up | Full build, texture, color, lighting and written approval. | Federal guide: 96 inch square full-thickness field mock-up. |
| 1 General | Meeting and sequencing | Owner, general contractor, installer and manufacturer coordination. | Set a project-specific meeting date, access plan and hold points. |
| 1 General | Warranty | Scope, parties, start date, exclusions and notice procedure. | Federal selectable example: two years; not a DTI warranty. |
| 2 Products | System | Type and complete build for each exposure zone. | Federal troweled example: 3/16 inch ± 1/16 inch; not a universal build. |
| 2 Products | Layers | Primer, body or mortar, aggregate, grout and topcoat. | Check compatibility of the complete system, including moisture treatment. |
| 2 Products | Properties | Relevant test methods, conditions and acceptance criteria. | Use actual product data; do not compare results from unlike methods. |
| 2 Products | Cove and joints | Height, radius, movement, drains and transitions. | Select and draw compatible details for the room and wall construction. |
| 2 Products | VOC | Applicable limits and compliant product data. | Confirm the project's jurisdiction and selected product category. |
| 3 Execution | Moisture | Method, conditioning, locations, report and system-specific limits. | Federal options: 75% RH; 3 or 4.5 lb/1,000 sq ft/24 h emission. |
| 3 Execution | Concrete age | Selected system's age and substrate conditions. | Federal guide: 28 days; reviewed polyurethane cement: typically 7 to 10 days. |
| 3 Execution | Profile | Mechanical preparation and verified CSP for the actual system. | Manufacturer guide: typical CSP 3 to 5; current product sheet controls. |
| 3 Execution | Adhesion | Substrate qualification and coating test criteria stated separately. | Manufacturer substrate example: 218 psi (1.5 MPa); D7234 is a test, not that limit. |
| 3 Execution | Environment | Air, slab, dew point, humidity, lighting and records. | Federal troweled example: dry substrate at least 60°F at application start. |
| 3 Execution | Cure | Foot, rolling, wet-cleaning and chemical-service release. | Use the selected system's conditions and written criteria. |
| 3 Execution | Acceptance | Thickness, surface condition, agreed testing and repairs. | Federal topping example: 1/8 inch in 8 feet; distinct from FF/FL. |
| 3 Execution | Protection | Compatible coverings and coordination with following trades. | Approve materials and removal timing without damaging the finish. |
Use the existing pre-spec consultation link to discuss the slab checklist and the resinous-flooring scope together. Agree on review deliverables, warranty terms and project acceptance in writing; the outline is not a completed specification or a promise of particular DTI services.
Coordinate phased warehouse repairs without shutdown, commercial kitchen details, spall and joint repairs and manufacturing systems by zone.
Frequently Asked Questions
What should be included in a warehouse floor specification?
A complete warehouse floor specification must include project-specific slab thickness, concrete strength and joint/load-transfer design set by the structural designer; flatness/levelness requirements (FF/FL per ASTM E1155 for random traffic; separately specified F-min requirements for defined traffic); surface preparation and moisture criteria set by the selected system manufacturer; and the coating or polishing system.
What PSI concrete is needed for a warehouse floor?
The structural designer must specify concrete strength for the actual slab, wheel and rack loads, joints and support conditions. A generic PSI band is not an acceptance criterion. The coating manufacturer's substrate requirements must also be met; a coating does not establish structural capacity.
Why do warehouse floor specifications fail?
Most specification failures come from incomplete specs, not wrong materials. Common gaps include missing flatness requirements for defined-traffic aisles, no joint load transfer design, inadequate moisture mitigation, and no surface prep standard. A floor spec is either complete or it isn't; partial specs create the most expensive failures because problems appear after the pour.
What CSI section covers resinous flooring?
Use Section 09 67 23 as the resinous-flooring framework, organized into General, Products and Execution. The reviewed federal 09 67 23.13 guide covers a specific troweled system. Specify submittals, qualifications, mock-up and warranty; then the complete build, substrate criteria, conditions, cure and acceptance. Edit guide examples for the project.
What moisture limit should a resinous flooring spec use?
Use the selected system manufacturer's written limit and applicable test procedure. The federal guide offers 75% RH and emission options of 3 or 4.5 lb per 1,000 sq ft per 24 hours. These are selectable examples, not universal ASTM limits. Investigate excessive moisture and specify an approved compatible response.
What concrete surface profile does a resinous floor need?
Use the selected primer and flooring system's current preparation requirements. One manufacturer guide gives CSP 3 to 5 as typical but directs users to product data. Require mechanical preparation and profile verification, including edges and repairs. Do not assign a universal profile from thickness alone or assume the equipment proves acceptance.
Sources
- Federal guide specification: troweled resinous flooring
- Manufacturer guide: substrate assessment and surface preparation
- Manufacturer data: polyurethane cement and young concrete
- ASTM F2170: in-situ relative humidity measurement
- ASTM F1869: calcium-chloride moisture vapor emission test
- ASTM D7234: pull-off adhesion of coatings on concrete
- ASTM E1155/E1155M: floor flatness and levelness numbers